Public procurement in Tanzania
- Main law
- Public Procurement Act 2023, Act No. 10 of 2023, assented 29 September 2023 1
- In force
- 17 June 2024, under Government Notice No. 455 of 7 June 2024 2
- Earlier law
- Public Procurement Act 2011, repealed by the 2023 Act 1
- Regulator
- Public Procurement Regulatory Authority (PPRA), section 8 1
- Appeals body
- Public Procurement Appeals Authority (PPAA), section 112 1
- Complaint window after notice of intention to award
- Five working days, section 69(4) 1
- PPAA decision time
- Within 40 days of registration, per PPAA guidance 6
- e-procurement
- Use of NeST required for all procurement, per PPRA 2
Law and regulator
The Public Procurement Act 2023 was assented to on 29 September 2023 and repeals the Public Procurement Act of 2011 1. PPRA published an English translation under Government Notice No. 813, dated 20 September 2024 1. PPRA reported on 12 June 2024 that the law would take effect on 17 June 2024 under Government Notice No. 455 2.
Section 8 continues the Public Procurement Regulatory Authority as a body corporate 1. PPRA says it was set up in May 2005 after the Public Procurement Act 2004, taking over from the Central Tender Board 3. Its functions include monitoring compliance, issuing standard tender documents and publishing procurement opportunities and awards 3.
PPRA said the 2023 law makes use of the National e-Procurement System of Tanzania (NeST) mandatory for all procurement and gives PPRA power to set price caps 2.
Procurement methods
Section 75(1) says entities must use competitive tendering, with the specific method set by regulations by type and value of the purchase 1. Section 3 defines competitive tendering as inviting suppliers, contractors or consultants to compete in submitting priced tenders 1.
- Restricted tendering is allowed where suppliers are prequalified, where urgency makes open tendering impracticable, or where social objectives call for local community participation, under section 75(2) 1.
- Urgency counts only if it was not foreseeable and not caused by the entity's own delay, and the entity must record its reasons, under section 75(3) 1.
- Seasonal goods such as grain, fuel and fertiliser are bought on a seasonal basis, under section 75(4) 1.
- Force account is covered in section 76 and now has a threshold, per PPRA 1,2.
- Consultants are selected under section 92 1.
Emergency, direct and single source purchases
Section 77 lets the accounting officer authorise emergency procurement in the public interest 1. It must meet one of three tests: a threat to life, health or safety from a disaster, irreparable harm to government functions or public property, or an urgent need for health commodities 1. Limits, methods and advertising rules may be waived, but tender evaluation and the accounting officer's approval may not 1.
Section 78 lets an entity buy directly from a manufacturer, dealer, wholesaler or service provider to get value for money on price, quality and delivery 1. The Minister may make regulations listing the goods and services that qualify and the procedure 1.
Section 69(5) names the single source method among methods exempt from the notice of intention to award 1. The Act text reviewed for this page does not list single source conditions in one section 1.
Complaints and appeals
After a tender decision, the accounting officer must send all tenderers a notice of intention to award, and tenderers have five working days to complain, under section 69(4) 1. Sections 119 to 125 cover the right to review, complaints to the accounting officer, appeals to the Appeals Authority and judicial review 1.
The PPAA guidance page says an appeal against an accounting officer's decision is due within five working days of learning of it 6. An appeal against blacklisting by PPRA is due within 21 days 6. Section 72(6) of the Act gives the same 21 days for debarred tenderers 1. The PPAA says it decides within 40 days of registering an appeal 6.
The PPAA handles disputes before and at award, and it does not handle complaints about contract implementation 5. Its home page links to the Act, the regulations, the appeals rules and the fee schedule 4.
PPPs and unsolicited proposals
The Public Private Partnership (Amendment) Act 2023, Act No. 4 of 2023, was published on 14 July 2023 7. It amends section 15 of the principal PPP Act 7.
Under the amended section 15(3), the Minister may exempt a project from competitive bidding on the recommendation of the PPP Steering Committee 7. One of three conditions must apply: urgent need with other procurement impracticable and not foreseeable, intellectual property rights held by the private party over key technology, or exclusive rights with no reasonable alternative 7. Under section 15(4), once an unsolicited project is exempted, the Government and the proponent negotiate the agreement 7.
Common questions
When did the Public Procurement Act 2023 take effect?
On 17 June 2024, under Government Notice No. 455 of 7 June 2024, as reported by PPRA 2.
How long does a bidder have to complain in Tanzania?
Five working days after the notice of intention to award, under section 69(4) 1.
Who hears procurement appeals in Tanzania?
The Public Procurement Appeals Authority, established under section 112 of the 2023 Act 1. Appeals go to its Executive Secretary in Dodoma 6.
Can a PPP be awarded without a tender?
Yes, in limited cases. The Minister may exempt a project from competitive bidding where one of three conditions in section 15(3) of the amended PPP Act applies 7.
Rules and fees change. Check the official site linked above before you apply or pay. Spotted an error? Email hello@procurementrules.org with the official link.
Sources
- PPRA Tanzania: The Public Procurement Act 2023, English translation, GN No. 813 (20 September 2024)
- PPRA Tanzania: New public procurement law to take effect on June 17, 2024 (12 June 2024)
- PPRA Tanzania: Background information (accessed 20 October 2026)
- Public Procurement Appeals Authority: home page (accessed 20 October 2026)
- Public Procurement Appeals Authority: Functions of the Appeals Authority (accessed 20 October 2026)
- Public Procurement Appeals Authority: Jinsi ya kukata rufaa, how to lodge an appeal (accessed 20 October 2026)
- Ministry of Finance Tanzania: The Public Private Partnership (Amendment) Act 2023, Act No. 4 of 2023 (14 July 2023)
Related
- Single-source procurement explained
What direct or single-source procurement is, when the UNCITRAL Model Law and World Bank rules allow it, and how Kenya, South Sudan and Uganda apply it.
- Public procurement in Kenya
Kenya's procurement law, methods, direct procurement rules under section 103, the Review Board, and privately initiated PPP proposals.
- Public procurement in Uganda
Uganda's PPDA Act as amended, the PPDA Authority, procurement methods, direct procurement conditions and appeals to the PPDA Appeals Tribunal.
- Public procurement in South Sudan
South Sudan's Public Procurement and Disposal of Assets Act 2018, the Authority, methods, single-source rules, and audit and IMF findings.